QS newbie
Performance bond
Mon Dec 5, 2011 2:22pm
165.202.4.150

What would be the estimated amount of the extra costs due to non-performance that should be covered by the performance bond.


    • Performance BondK C Tang, Thu Dec 15 4:20pm
      The amount of extra costs would be difficult to estimate. It would be affected by the degree of closeness of the actual payment to the actual progress, the time stage of the construction, the... more