Contract period refers to the period of between Works Commencement Date and Works Completion Date stated in the Appendix, and it covers the extended period, if any, until the issue of P.C. Cert.

a) Is the contract period deemed as construction period although there is no defined term stated in SFC.

b) Could we otherwise interpret that contract period starts from the date of Contract's award until the issue of Final Cert. which is deemed to be of conclusive to the Contract.


    • Contract Period vs Construction PeriodK C Tang, Thu Dec 15 2:11pm
      The Old and New SFBC do not have a definition for "the Contract Period" or "the Construction Period". The Contract Period is generally understood as the period stated in calendar days or, in rare... more
      • Contract Period vs Construction PeriodK C Tang, Thu Dec 15 2:36pm
        If the Contract Period is extended, we would usually call it "extended Contract Period" as distinguished from "original Contract Period" if such distinction is desirable. K C Tang