QS APC Forum by HKIS Young Surveyors Group
Lease this WebApp and get rid of the ads.
K C Tang
Contract Period vs Construction Period
Thu Dec 15, 2011 2:36pm
59.152.251.234

If the Contract Period is extended, we would usually call it "extended Contract Period" as distinguished from "original Contract Period" if such distinction is desirable.

K C Tang

  • Contract Period vs Construction PeriodK C Tang, Thu Dec 15 2:11pm
    The Old and New SFBC do not have a definition for "the Contract Period" or "the Construction Period". The Contract Period is generally understood as the period stated in calendar days or, in rare... more