Dear KC,
Background information:
During tender analysis (lump sum drawings and specification with SOR), an arithmetical error was found in one of the tenders which leads to adjustment factor (a discount factor).
At this moment, a post tender addendum issued due to revised scope of works where some of the original works were omitted and new items were added.

The question is whether the discount factor shall or shall not applied to the omission and addition items.