What is DRM, and how it actually apply in construction project?

What is it relationship with EOT?

  • Delay Recovery MeasuresK C Tang, Sun Aug 7 5:50pm
    I think clause 26.4 intends to say that extension of time should still be granted for delays not recovered by AGREED delay recovery measures, but is insufficient to deal with cases where the AGREED... more
    • Delay Recover Measure & EOT — undergrad, Wed May 4 11:44am
      • Delay Recovery MeasuresK C Tang, Thu May 5 2:41am
        Delay recovery measures are measures to recover delays. They are usually called acceleration measures. In the Standard Form, the delays refer to those not caused by the Contractor, essentially delays ... more